Construction site update

Construction site update

Construction site update

New MAXXOM Oberhofen building

The new MAXXOM headquarters in Oberhofen is taking shape more and more! Since our last construction photo, work has been busily progressing and we are heading full steam towards the planned move-in in August. The anticipation couldn’t be greater!

Next Steps

  • June/July: Floor coating, installation of electrical and pneumatic systems, the fire-protected IT server and the access control system.
  • End of July: Start of interior setup.
  • August: Move-in with the relocation of milling centers and the machine park, installation of an intelligent inventory management system and e-charging stations for customer and employee vehicles.
  • Autumn: Installation of a PV system with a buffer storage.